📩 Contact via Email

✉️ Send email directly

💬 WhatsApp

WhatsApp QR Code

Scan to add, consult anytime

📱 Open chat directly

💖 WeChat

WeChat QR Code

Scan to add WeChat, one-on-one communication

Why Your 6×1000kW Diesel Station Wastes Fuel at Part-Load — and How a 1MW/2MWh BESS Hybrid Fixes It

Powering Progress with Innovation

Imax Power — Delivering Energy Solutions for a Better Tomorrow

Note: This case study is based on typical project configurations and industry experience for illustrative purposes.

Project Background & Requirements

A remote industrial site operates six 1,000 kW diesel generators running 24/7. No utility grid. No solar. The station was originally sized for peak demand but spends most of its hours at part-load — a textbook inefficient operating regime for diesel gensets.

The site owner approached Imaxpower with a clear requirement: deploy a 1 MW PCS + 2 MWh battery energy storage system (BESS) to work alongside the existing diesel generators. The objectives were threefold:

  • Peak shaving — discharge the battery during daytime high-load hours to keep diesel generators in their 60–80% efficient operating band.
  • Overnight recharge — charge the battery during low-demand hours when diesel marginal cost per kWh is lowest.
  • Critical load backup — if any generator trips offline, the storage system must pick up critical loads (PLCs, servers, VFDs) without interruption.

The customer explicitly required a diesel-only hybrid configuration — no PV, no grid connection. This simplified the architecture but placed stricter demands on the PCS grid-forming capability and EMS diesel-hybrid logic.

Key Engineering Challenges

1. Diesel Part-Load Inefficiency and Fuel Waste

Diesel generators achieve their best specific fuel consumption (typically 200–220 g/kWh) at 60–80% rated load. Below 50% load, efficiency drops sharply — some units consume 30%+ more fuel per kWh at 30% load. With six 1 MW gensets and a variable load profile, the station was frequently running 2–3 units at part-load just to maintain redundancy, wasting fuel and accelerating engine wear.

2. Seamless Transition Between Grid-Tied and Off-Grid Modes

When a diesel generator trips, the PCS must transition from grid-following (synchronized to the diesel bus) to grid-forming (creating its own stable AC reference) before critical loads detect an interruption. Conventional PCS units require 20–50 ms for this transfer — enough to cause PLCs and servers to reboot. The engineering requirement was sub-10 ms passive transfer and 0 ms active transfer, which demands full-digital DSP+CPLD control and a high-speed static transfer switch (STS).

3. Battery Longevity Protection Under Daily Deep Cycling

The system performs one full charge-discharge cycle per day (100% → 20% → 100%). Without proper SOC management, this deep cycling would degrade LFP battery capacity to 80% SOH within 3–4 years instead of the rated 6,000+ cycles. The EMS must enforce hard SOC floors (20%) and ceilings (100%), implement cell balancing across racks, and use ramp-controlled charge/discharge to avoid high C-rate stress.

Our Engineering Solution

System Architecture

Imaxpower designed a two-unit parallel architecture: two MSP500HCG2 500 kVA hybrid PCS cabinets operating in parallel, each paired with a 1 MWh LFP battery rack, delivering a combined 1 MW / 2 MWh system. This was a deliberate engineering choice over a single 1 MW centralized PCS:

  • N+1 redundancy — if one PCS module faults, the other continues supplying 500 kW to critical loads.
  • Modular scaling — the same platform deploys at 500 kW / 1 MWh or expands to 1.5 MW / 3 MWh (up to 3 units parallel).
  • Decentralized fault tolerance — string architecture means each PCS connects to its own battery cluster independently; no DC combiner box, no shared failure domain.
  • Logistics — 500 kW cabinets install with standard site equipment; no heavy crane work required.
System topology diagram of 1MW 2MWh diesel hybrid energy storage system with PCS battery EMS and critical loads
Figure 1 — System topology: 6× diesel generators → AC bus → 2× MSP500HCG2 PCS in parallel (1 MW) → DC bus → 2× 1 MWh battery racks. The EMS coordinates genset start/stop, PCS charge/discharge, and SOC setpoints. Critical loads receive sub-10 ms backup.

The MSP500HCG2 is an all-in-one cabinet integrating bidirectional AC/DC PCS (three-level topology, 500 kVA rated / 550 kVA peak), on-board EMS with diesel-hybrid mode, STS for seamless transition, AC distribution, lightning protection, and IP54 thermal management rated for −30 °C to +60 °C ambient.

Component Selection

Component Selection Key Specification Engineering Rationale
PCS 2× Imaxpower MSP500HCG2 500 kVA each, 99.3% efficiency, <10 ms switch-over Parallel N+1 redundancy; high efficiency minimizes round-trip losses
Battery 2× 1 MWh LFP racks 680–950 V DC, integrated BMS Wide voltage window matches PCS; LFP offers 6,000+ cycle life
EMS Imaxpower full-stack self-developed DSP+CPLD control, diesel-hybrid mode, cloud OTA Enforces SOC windows; coordinates genset load sharing; no third-party black box
Thermal IP54 fan-cooled (standard) / liquid-cooled option −30 °C to +60 °C operating range Outdoor-rated for remote sites; no climate-controlled room required
DC/DC (optional) Imaxpower 125 kW bidirectional DC-DC 1250 V port, ≤5% current ripple For future PV integration or multi-voltage battery clusters

The 24-hour operating strategy is managed entirely by the EMS:

24-hour operating cycle chart showing site load PCS charge discharge power and battery SOC for diesel hybrid energy storage system
Figure 3 — 24-hour operating cycle: daytime PCS discharges (orange) to shave peak load, SOC descends 100%→20%; overnight PCS charges from diesel bus (green), SOC recovers to 100%. EMS manages ramp-controlled power to avoid genset frequency deviation.
  • Daytime (06:00–19:00): Peak shaving discharge. EMS monitors AC bus load; when load exceeds the optimal diesel band, PCS discharges to shave the peak. Stops at 20% SOC floor.
  • Overnight (22:00–06:00): Controlled recharge. PCS charges from diesel bus with current-limiting and ramp-control to avoid genset load steps. Stops at 100% SOC ceiling.
  • Backup mode (generator fault): Grid-forming off-grid. PCS transitions to grid-forming in 0 ms (active) / <10 ms (passive), supplies critical loads up to 1 MW. EMS signals standby gensets to start; once stable, PCS resynchronizes seamlessly.
  • Standby: BMS cell balancing, SOC/SOH monitoring, cloud telemetry.

How to Select the Right Configuration

Many EPC contractors ask: should I use a single 1 MW centralized PCS or two 500 kW modular units in parallel? The decision depends on four factors:

Factor Single 1 MW Centralized PCS 2× 500 kW Modular Parallel Recommendation
Redundancy Single point of failure N+1 redundancy (500 kW fallback) Modular for critical loads
Footprint Smaller per kW Slightly larger total Centralized for space-constrained
Scalability Fixed capacity Expand to 1.5 MW (3 units) Modular for phased deployment
Logistics Requires crane & dedicated foundation Standard forklift installation Modular for remote sites
Cost Lower upfront per kW Slightly higher upfront Centralized for budget-first

For this remote diesel-hybrid site with critical loads and limited installation infrastructure, the 2× 500 kW modular parallel configuration was the clear choice. For utility-scale installations above 2 MW with dedicated electrical rooms, Imaxpower also offers centralized PCS up to 1.725 MW.

The same 1 MW / 2 MWh building block serves multiple application classes:

Application Peak Shaving Load Following Black Start Grid-Forming Seamless Transfer
C&I Peak Shaving
Microgrid (Diesel+Storage)
Off-Grid Mining / Construction
Critical Backup / UPS
V2G / EV Fleet Depot
✓ Full capability · ◐ Partial / configuration-dependent · — Not applicable

Measured Results & Performance

Based on typical project configurations and field validation data, the 1 MW / 2 MWh diesel-hybrid system delivers the following performance:

Charging efficiency comparison chart showing Imaxpower PCS at 99.3 percent versus industry average 97.5 percent with annual fuel energy savings
Figure 2 — At 99.3% round-trip charging efficiency, the MSP500HCG2 saves ~8,400 kWh of fuel-energy per MWh of battery annually versus a 97.5% benchmark, directly reducing diesel consumption.
Metric Value Industry Benchmark Impact
PCS charging efficiency > 99.3% 97–98% ~8,400 kWh fuel saved/MWh/year
Grid/off-grid switch-over 0 ms active / <10 ms passive 20–50 ms Critical loads never drop out
THDi (>30% load) < 3% < 5% Clean power for sensitive equipment
Operating temperature −30 °C to +60 °C 0 °C to +40 °C Outdoor deployment in extreme climates
Protection rating IP54 IP20 (indoor) Dust & water resistant for outdoor
Max parallel units 3 (1.5 MW total) 1–2 Modular capacity expansion
Battery voltage range 680–950 V DC 500–850 V DC Compatible with LFP & NMC chemistries

Project Note: In a comparable 2 MWh diesel-hybrid deployment in Southeast Asia, the system achieved a 28% reduction in diesel generator runtime during peak hours, with the PCS maintaining >99% round-trip efficiency across 365 daily cycles. The EMS-enforced 20–100% SOC window is projected to yield >6,000 cycles before reaching 80% SOH.

Need a Similar System Design?

If you’re planning a microgrid, BESS, or diesel-hybrid project, our engineering team can help you design the optimal system based on your specific load profile, genset configuration, and site conditions.

Send us your project specs — load curve, generator ratings, site ambient conditions, and required backup capacity — we’ll propose a solution within 24 hours.

Contact: info@imaxpwr.com | Tel/WhatsApp: +86-13760212825 | www.imax-pwr.com

Key Lessons Learned

  • Don’t oversize the PCS. A 1 MW PCS for a 6 MW diesel station is sufficient for peak shaving — the goal is to keep diesels in their efficient band, not replace them entirely.
  • SOC windows are non-negotiable. Allowing discharge below 20% or charging above 100% accelerates battery degradation. The EMS must enforce these as hard limits, not suggestions.
  • Ramp control protects generators. Sudden PCS charge/discharge steps cause genset frequency deviation. Always use ramp-controlled power profiles (5–10 kW/s) when transitioning between states.
  • Parallel modular beats single centralized for remote sites. N+1 redundancy and standard logistics outweigh the small footprint advantage of a single large PCS when the site is hard to access.
  • IP54 matters more than you think. Remote sites are dusty, humid, or both. An IP20 indoor-rated PCS requires a climate-controlled room — adding cost and complexity that IP54 outdoor-rated units eliminate.

FAQ

Q: Can a diesel hybrid energy storage system work without solar or grid connection?

A: Yes. The system described uses only diesel generators + PCS + battery storage. The PCS charges from the diesel AC bus during low-demand hours and discharges during peak hours. No PV or grid connection is required. The key requirement is a PCS with grid-forming capability and an EMS with diesel-hybrid control logic.

Q: How do I size the PCS and battery for my diesel station?

A: As a starting point, size the PCS at 15–25% of total diesel capacity (for a 6 MW station, 1–1.5 MW PCS). Size the battery for 2 hours of PCS discharge at rated power (1 MW PCS → 2 MWh battery). Refine based on your actual load curve — if peaks are short (1–2 hours), a smaller battery may suffice; if you need longer backup, increase capacity. Send us your load curve for a precise sizing calculation.

Q: What happens to critical loads when all diesel generators fail?

A: The PCS transitions to grid-forming off-grid mode in 0 ms (active transfer) or <10 ms (passive transfer), supplying critical loads directly from the battery at up to 1 MW / 1.1 MW peak. The EMS simultaneously sends start signals to standby generators. Once a generator stabilizes (typically 10–30 seconds), the PCS resynchronizes and transfers back to grid-following mode — all without load interruption. The 2 MWh battery provides up to 2 hours of backup at 1 MW discharge, or longer at reduced load.

About the Author

This article was reviewed by Ethan Li, an energy storage system specialist with experience in PCS, DC/DC converters, and microgrid design. With a background in power electronics and field commissioning of BESS projects across Southeast Asia, the Middle East, and Africa, Ethan focuses on translating engineering requirements into deployable system architectures.

About IMAXPWR

Imaxpower (Imax Power Technology Co., Ltd.) is a China national high-tech enterprise headquartered in Shenzhen, specializing in integrated energy storage products and system solutions. Founded in 2015, the company has delivered 999+ projects worldwide with a 99% customer recognition rate.

The R&D team comprises senior experts from State Grid, Xuji Group, Emerson, and Kehua Hengsheng, with 20+ years of power electronics experience. Imaxpower develops full-stack self-developed PCS, BMS/EMS, bidirectional DC/DC converters, and all-in-one BESS cabinets, covering 30 kW to 2 MW+ system deployments.

Imaxpower product portfolio power map showing PCS modules BESS cabinets and centralized PCS from 30kW to 2MW
Figure 5 — Imaxpower product portfolio: from 30 kW bidirectional modules to 1.725 MW centralized PCS, with all-in-one BESS cabinets from 66 kWh to 522 kWh. The 1 MW / 2 MWh diesel-hybrid configuration (star) sits at the intersection of C&I and microgrid power needs.

Products are certified to UN38.3, IEC, UL, CE, and RoHS standards, shipping to Europe, North America, Southeast Asia, the Middle East, and Africa without re-engineering. The company offers full customization — from system design and engineering to O&M services — tailored to specific project requirements.

Contact: Coco | Tel/WhatsApp/WeChat: +86-13760212825 | Email: info@imaxpwr.com | www.imax-pwr.com

 

Get In Touch​

We will reply you in 24 hours​

Get in touch with us for tailored energy solutions.

Submit your inquiry and let us help you find the best solutions for your energy needs. Quick response guaranteed!

Talk to an Engineer
Join 100+ Industry Leaders – Get Your Custom Solution