Microgrid Project
Region and Country: Romania, Europe
Client: Manufacturing Factory
Project Configuration: 400kW/931.84kWh BESS (Battery Energy Storage System) + EMS (Energy Management System) + 600kW Solar System + STS (Static Transfer Switch)
Project Time: 2024
Application Solution: Industry and Commerce
Applied EMS: Power and Control Database
Applied Energy Storage System: IMEXES215 Machine Cabinet (This specifies the model of the energy storage system cabinet)
Application Services: Engineering, Consultation
Application Logic: Peak shaving, seamless switching between the grid and the energy storage system, load transfer, and power quality adjustment